Error: Field cannot left blank.
Error: Invalid entry. Do not use equal signs [=] or colons [:].
Error: Field cannot left blank.
Error: Invalid entry. Do not use equal signs [=] or colons [:].
Undergrounding & system upgrades
PG&E is working to install thousands of miles of powerlines below ground in high wildfire risk areas. We are also upgrading our electric system by installing strong poles and covered powerlines. This work will help keep customers and communities safe.
How we determine where to complete wildfire safety work
The types of system improvements we consider include:
- Moving powerlines underground
- Installing strong poles
- Covering powerlines
- Trimming trees
These are just some of the layers of protection that help keep customers safe. Learn more about our other layers of wildfire protection. Visit PG&E's Community Wildfire Safety Program.
Benefits of undergrounding for wildfire safety
Our undergrounding efforts involve moving sections of powerlines below ground. This eliminates nearly all wildfire ignition risk from that line. It also improves reliability.
Undergrounding is safe, strong and more cost-effective in the long term. This proven process:
- Reduces nearly all wildfire risk in a given location
- Improves reliability and limits outages
- Decreases the need for future tree and vegetation work
- Lowers maintenance and operating costs
Note: After we complete this work, customers will continue to see other equipment overhead. In most cases, this includes telephone lines or lower-voltage powerlines connecting to individual homes or businesses.
Benefits of system upgrades for wildfire safety
We are upgrading overhead poles and powerlines to reduce wildfire risk. We describe these changes as system upgrades, or overhead hardening. This work reduces ignition risk by nearly 64% on a line once completed. When used with other wildfire safety tools, additional risk is reduced. It is also a useful tool in areas where powerlines cannot be moved underground.
These efforts are targeted in high wildfire-risk areas and can include:
- Replacing bare powerlines with strong covered powerlines
- Installing strong poles
- Installing more poles to support the weight of covered powerlines
- Removing overhead poles and lines that are no longer needed
Note: After we complete this work, customers may also see remaining poles for phone, internet or other electrical lines.
What can I expect during this work?
We will keep you informed if we identify your area for wildfire safety work. Projects that include moving powerlines underground typically take 12 to 24 months to complete. The installation of strong poles and covered powerlines typically takes 6 to 18 months to complete*.
In your neighborhood you may see:
* Phases 1 through 3 may take 1 to 18 months. Phases 4 and 5 may take 2 to 3 months each.
For your safety, all crews and contractors conducting this work are happy to provide photo ID on request.
Learn more about our wildfire safety work
Undergrounding for public safety
The scope of each undergrounding and system upgrade project can vary. This means permitting and easement needs also vary across projects.
- If a permit is needed, PG&E will work with local permitting agencies before moving forward with construction.
- If an easement or land use agreement is needed, PG&E’s land team will work directly with individual property owners.
- If you have questions about permitting, easements or land use agreements for work in your area, email undergrounding@pge.com.
Customer and community resources
Undergrounding resources for your county
Additional information or a map is available for each county by clicking the links below:
- Alameda (PDF)
- Amador (PDF)
- Butte (PDF)
- Calaveras (PDF)
- Contra Costa (PDF)
- El Dorado (PDF)
- Fresno (PDF)
- Glenn (PDF)
- Kern (PDF)
- Lake (PDF)
- Madera (PDF)
- Mariposa (PDF)
- Mendocino (PDF)
- Napa (PDF)
- Nevada (PDF)
- Placer (PDF)
- Plumas (PDF)
- San Mateo (PDF)
- Santa Cruz (PDF)
- Shasta (PDF)
- Sierra (PDF)
- Solano (PDF)
- Sonoma (PDF)
- Tehama (PDF)
- Tuolumne (PDF)
- Yuba (PDF)
- All undergrounding & system upgrade maps (PDF)
Find information about wildfire safety work in your area by visiting our wildfire safety progress map.
* Data as of October 1, 2024. Some undergrounding projects include associated system upgrade mileage. This map is for illustrative purposes. Forecasts can change as our risk model evolves to address the greatest wildfire risk. Forecast miles also exceed annual targets. Mileage in a community may increase or decrease due to access, weather, permitting or other constraints. In most cases, if a project is not completed during the year originally identified, it will continue through planning/construction phases during subsequent years. Mileage represents projects that will be energized in a given year. Construction for a project may begin before the year of energization and final property and road restoration work may occur after the year of energization.
Resources - learn more about this work
Undergrounding and overhead system upgrade videos
Learn more about our undergrounding and system hardening upgrades work by viewing the videos below.
Frequently asked questions
- Find information on planned and completed undergrounding and system upgrades projects on our wildfire safety progress map.
- Find additional maps or information for each county where undergrounding work is planned on the "Undergrounding resources for your county" tab
We will keep you informed if we identify your home or business for wildfire safety work. We may reach out using letters, emails, text messages and phone calls.
If you have any questions, email undergrounding@pge.com or call 1-877-265-1399.
- We are prioritizing undergrounding and system upgrades in high fire-risk areas.
- Because we are focused on reducing wildfire risk, we are not taking community or customer requests for undergrounding or system upgrades as part of this program.
- That said, PG&E does have other non-wildfire safety related programs for moving powerlines underground.
- There is also the Rule 20 (A, B and C) Program.
- These programs allow customers, cities, counties or other individuals to request undergrounding.
- This work is funded by the applicant or in some cases work credits (only agencies can use these work credits).
- These programs prioritize our undergrounding and system upgrades work in areas where we can have the greatest impact on reducing wildfire risk.
- We have already completed 800+ miles of the 1,600 miles of undergrounding we plan to complete in the highest fire-risk areas by the end of 2026.
- We will continue to work with California regulators to finalize plans for future years.
- This will be done through our long-term undergrounding plan.
- These plans will substantially reduce wildfire risk across our service area.
- We have also completed 1,700+ miles of system upgrades (strong poles and covered powerlines) and plan to install another 650+ miles through 2026.
- We will continue to scope work and identify undergrounding and system upgrade miles for future years. Work will first go to the highest-risk circuits.
Undergrounding and system upgrades are just two of the many layers of protection that reduce wildfire risk. We will also:
- Manage trees and shrubs to ensure they grow a safe distance from powerlines.
- Employ our network of weather stations and cameras to better detect extreme weather and wildfires.
- Utilize Enhanced Powerline Safety Settings and more.
To see where many of these layers of protection are in use in your community, visit our wildfire safety progress map.
Distribution powerlines are the smaller powerlines that carry electricity through neighborhoods. Transmission lines are the larger lines that carry power long distances.
Data shows that these distribution powerlines are at a higher wildfire risk than transmission lines. Transmission lines also have larger clear spaces around them from vegetation and on the ground, making wildfire risk lower. This is why PG&E’s undergrounding and system upgrade work targets distribution lines.
Of course, PG&E also has strategies to lower wildfire risk on transmission lines. These include:
- Conducting risk-based equipment inspections and repairs.
- Replacing lines when needed.
- Addressing trees and vegetation under and around transmission lines.
- Utilizing powerline safety settings.
- De-energizing lines as needed during Public Safety Power Shutoffs (PSPS).
Other undergrounding information
PG&E has multiple programs that underground powerlines. Our work to move powerlines underground to reduce wildfire risk is one program. There are also the Rule 20 (A, B and C) Program.
Rule 20 has three sections (A, B and C). Rule 20 sections are determined by the type of project and who pays for the work. Rule 20 projects also typically involve undergrounding all above-ground utilities and poles (including telecommunication lines), which is different than wildfire safety-related undergrounding.
Rule 20-related undergrounding work can be requested by:
- Cities
- Counties
- Other municipalities
- Developers
- Individuals or groups of customers
Work is completed by following the California Public Utilities Commission (CPUC) Rule 20 electric distribution tariff guidelines.
For more information on Rule 20 please refer to the below documents:
- Download the PG&E Electric Rule 20 Guidebook (PDF)
- Download the latest PG&E Rule 20 Annual Report (per ordering paragraph 14 of D.21-06-013) (XLSX)
Note: The CPUC decided in June 2023 to end the Rule 20A program by December 31, 2033. Rules 20B and 20C are not affected by this decision.
November 2024: PG&E Reaches Significant Undergrounding Milestone, Burying More than 800 Miles of Lines in High Wildfire-Risk Areas
August 2024: PG&E Undergrounding Contractors Save Women, House from Fire
June 2024: New Online Map Lets Customers See Wildfire Prevention Progress in their Hometowns
February 2024: Climate-Tech Solutions Aimed at Achieving a Clean Energy Future
See our progress and future plans
Data as of 1/13/2025
Since launching our 10,000-mile undergrounding program in 2021, we have:
- Constructed and energized more than 870 miles of underground powerlines
- Completed this work on time and on budget
- As of December 16, 2024, we reached our goal of moving 250 miles of powerlines underground in 2024.
View planned and completed undergrounding on the wildfire safety progress map.
System upgrade progress
Data as of 12/16/2024
We have installed 1,250+ miles of strong poles and covered powerlines since we launched our Community Wildfire Safety Program in 2018. As of December 16, 2024, we reached our goal of installing 70 miles of strong poles and covered powerlines in 2024. In some cases, this work included limited line removal.
View planned and completed system upgrades on the wildfire safety progress map.
10-Year Electrical Undergrounding Plan (EUP)
SB 884 Expedited Undergrounding Program Discovery/Data Requests
PG&E has responded to discovery or data requests relating to the filing of a 10-year Electrical Undergrounding Plan (EUP) under Senate Bill 884. Each discovery or data request from the California Public Utilities Commission (CPUC) Safety Policy Division (SPD) related to PG&E's EUP is included in the links below.
This page is updated weekly with the latest SPD discovery or data requests and responses.
Updated as of: January 14, 2025
Note: If there are no new responses in a given week, the date will not be updated.
Contact Us with Issues
Report any accessibility barriers you encounter by contacting undergrounding@pge.com. The mailbox is monitored during our business hours (Monday - Friday; 8 a.m. - 5 p.m.). We will respond within 3 business days.
CPUC Safety Policy Division (SPD)
Responses to IOU Balancing and Memorandum Account
SPD - Data Request 001 (ZIP)
SPD - Data Request 002 (ZIP)
SPD - Data Request 003 (ZIP)
Responses to GRC Depreciation Study Link
SPD - Data Request 004 (ZIP)
Responses to Undergrounding Capital Orders
SPD - Data Request 005 (ZIP)
Responses to Capital Accounting FAQ Documents
SPD - Data Request 006 (ZIP)
Responses to Revenue Requirements Follow-up Questions
SPD - Data Request 007 (ZIP)
Responses to Shared Poles Contracts/Lease Agreements
SPD - Data Request 008 (ZIP)
Responses to WMP Cost Reporting Template
SPD - Data Request 009 (ZIP)
Responses to Undergrounding Project Phases and Project Documents
SPD - Data Request 010 (ZIP)
SPD - Data Request 013 (ZIP)
Responses pertaining to PG&E's Mini-RO Models
SPD - Data Request 011 (ZIP)
SPD - Data Request 012 (ZIP)
Responses pertaining to External Funding
SPD - Data Request 014 (ZIP)
Contact us
Program contact information
For any questions related to undergrounding or installing strong poles and covered powerlines, email undergrounding@pge.com or call 1-877-265-1399. We will get back to you within 3-5 business days.
Vendor information
If you are a vendor interested in working with PG&E, email undergrounding@pge.com.
Services of interest may include, but are not limited to:
- Electric construction services
- Civil construction services
- Engineering services
- Engineering, procurement and construction services
- Other relevant support services
- Electric materials
Questions
Call the PG&E Undergrounding and System Upgrades Team at 1-877-265-1399 or email us at wildfiresafety@pge.com. Responses typically take 3-5 business days.
More on outages and safety
Outage preparedness and support
Stay prepared for power outages and get support.
Community Wildfire Safety Program (CWSP)
Find out how PG&E is making our system safer and more reliable.
©2025 Pacific Gas and Electric Company
©2025 Pacific Gas and Electric Company