Error: Field cannot be left blank.
Error: Invalid entry. Do not use equal signs [=] or colons [:].
This summary is not available. For more details, open this PDF.
- Still need assistance? Try the Help Center.
- Link accounts. Learn how to link your accounts or access more accounts.
- CARE. Find out if you qualify for a discount.
- Medical Baseline. Learn how to apply.
- Rebates. Explore PG&E rebates for your home.
- Outages. Report and view electric outages.
- Jobs/Careers. Find out about jobs at PG&E.
Error: Field cannot be left blank.
Error: Invalid entry. Do not use equal signs [=] or colons [:].
This summary is not available. For more details, open this PDF.
- Still need assistance? Try the Help Center.
- Link accounts. Learn how to link your accounts or access more accounts.
- CARE. Find out if you qualify for a discount.
- Medical Baseline. Learn how to apply.
- Rebates. Explore PG&E rebates for your home.
- Outages. Report and view electric outages.
- Jobs/Careers. Find out about jobs at PG&E.
Commercial projects
Common examples of projects include, but are not limited to:
- Multi-family residential – townhomes, condos, apartments
- Retail centers – strip malls, malls
- Businesses, office buildings, warehouses
- Research facilities, education facilities
- Telecom infrastructure
To know where there's capacity near your project site, visit Distributed Resource Planning (DRP) Data & Maps.
The Grid Resource Integration Portal is designed to help engineers and developers. The portal helps them find information on potential project sites for Distributed Energy Resources (DERs). The map includes hosting capacity, forecast data, grid needs, and other information about PG&E's electric distribution grid.
The information on these maps is illustrative and is likely to change or be modified over time. PG&E's electric distribution system is dynamic. Circuits on the distribution system change for various reasons. Examples include, but are not limited to, circuit upgrades, new loads, new DERs, new circuits, and seasonal switching. Over time, a single location may have different results due to these changes.
Resources
Switchboard Guide
Use this guide for support with your secondary switchboard installation.
Frequently asked questions
The following frequently asked questions (FAQs) apply to both overhead and underground service installations.
The FAQs are intended to help contractors and customers applying for or working on projects with PG&E understand PG&E processes and requirements. They also provide guidance on common issues during setup and inspection.
Download our Local Inspection Desk Contact List (PDF) for your local area's email address.
To make changes to an approved design, reach out to your PG&E Job Owner. Provide them with a mocked-up version of the new design using the existing drawings or plans. This might require you to also update your:
- Globals
- Site plans
- Elevation plans
- Single line diagrams
- Switchgear cut sheets and/or loads
The PG&E Job Owner will submit them to our External Estimator team on your behalf. If you receive approval on the mockups, then the revisions will be completed in about 30 days.
"Civil as-builts" are final substructure drawings. They show detailed electric underground infrastructure (substructures), including:
- Conduit lengths
- Enclosure and/or vaults
- Pad locations
- Redlines for any changes to substructure
Yes, all contractors must provide a copy of the "civil as-builts" at the final inspection. The plans must have a signature, date, and company name per PG&E Design Standards. To learn more about the process, speak with your PG&E Job Owner. They can provide more details about TD-2051P-10-B002, "Electric Operations AIF As-Built Acceptance Process."
If you are starting a home or business construction project, you may have service connection needs. You may be required to upgrade or move your gas service meter. PG&E can help you to meet technical requirements and coordinate your service change. Once you submit your application to PG&E, we will create a schedule to meet your service connection needs.
Examples of construction projects include:
- Adding a room or square footage
- Building a swimming pool
- Installing new commercial gas appliances
- Installing a tankless water heater.
Submitting your application
- Apply for additional gas meters using Your Projects.
- Upload all required documents, including permits (if applicable) in the online application.
Application review
- Once you submit your application, a dedicated PG&E Job Owner is assigned to you. This person will become the point of contact for you or your contractor. PG&E recommends that you contact a contractor to help you plan your service change.
- A PG&E Job Owner will contact you within five business days. You or your contractor will be asked to supply details of the project. Details of the project include scope, timeline, blueprints, and the load requirements for appliances. You will need to provide details about any appliances or equipment you plan to install. Your PG&E Job Owner can answer additional questions. They can inform you of issues you may not have taken into consideration. Issues can be potential costs or technical Design Standards.
- If payment for an engineering advance is required, your PG&E Job Owner will notify you at this time.
- If necessary, a field meeting will be scheduled. PG&E uses the information you supply during a phone or on-site meeting to prepare a project design.
Note: You are required to provide all mandatory documents and materials. Deliver them to your PG&E Job Owner. Avoid application cancellation by submitting the documents within 35 calendar days. The document deadline date is no later than 35 days after you submit the application. Complete the application review process with your PG&E Job Owner. Complete it within 66 calendar days from application submission. The review deadline date is no later than 66 days after submission. This process complies with CPUC timeline regulations.
PG&E prepares project design
During the project design phase, we identify your costs and prepare construction drawings. We share them with you for your review and approval.
Additional references
You or your contractor may need to refer to the Greenbook (PDF). It is a reference manual containing helpful information. The Greenbook includes additional information, such as technical specifications and drawings. The Gas Service section may be especially helpful when making changes to your gas service.
Trenching
- Upgrading underground gas lines may require the excavation of a trench. Your PG&E Job Owner will provide you with drawings that illustrate the trench route and specifications. Customers are responsible for trenching and permit costs.
- For more information about excavating a utility trench refer to the "Undergrounding Construction FAQs."
- Before you dig, call Underground Service Alert at 811, Monday through Friday from 6 a.m. to 7 p.m. except for holidays, or visit call811.
Contract execution and payment
- Along with the project design, you will receive a contract including an invoice for the project work to execute via DocuSign.
- Contracts must be executed within 90 days of receipt.
- Your contract, once executed, is valid for up to 12 months.
- Your design is valid for up to 18 months from issuance.
Construction scheduling
Work with your PG&E Job Owner to schedule any construction work to be completed by PG&E.
Inspections and meter connection
Arrange for the appropriate local government agency to inspect the gas line. Once it has passed inspection contact PG&E to schedule the meter connection.
If your home or business construction project requires the installation of new gas service, PG&E can help. Get help to meet technical requirements and coordinate your service installation. Once you submit your application to PG&E, we will create a schedule to meet your service connection needs.
Submitting your application
- Apply for new gas service using Your Projects.
- Upload all required documents, including permits (if applicable) in the online application.
Application review
- Once you submit your application, a dedicated PG&E Job Owner is assigned to you. This person will become the point of contact for you or your contractor. PG&E recommends that you contact a contractor to help you plan your new service installation.
- A PG&E Job Owner will contact you within five business days. You or your contractor will be asked to supply details of the project. Details of the project include scope, timeline, blueprints, and the load requirements for appliances. You will need to provide details about any appliances or equipment you plan to install. Your PG&E Job Owner can answer additional questions. They can inform you of issues you may not have taken into consideration. Issues can be potential costs or technical Design Standards.
- If payment for an engineering advance is required, your PG&E Job Owner will notify you at this time.
- If necessary, a field meeting will be scheduled. PG&E uses the information you supply during a phone or on-site meeting to prepare a project design.
Note: You are required to provide all mandatory documents and materials. Deliver them to your PG&E Job Owner. Avoid application cancellation by submitting the documents within 35 calendar days. The document deadline date is no later than 35 days after you submit the application. Complete the application review process with your PG&E Job Owner. Complete it within 66 calendar days from application submission. The review deadline date is no later than 66 days after submission. This process complies with CPUC timeline regulations.
PG&E prepares project design
During the project design phase, we identify your costs and prepare construction drawings. We share them with you for your review and approval.
Additional references
- You or your contractor may need to refer to the Greenbook (PDF). The Gas Service section may be especially helpful when making changes to your gas service.
Trenching
- Upgrading underground electrical lines may require the excavation of a trench. Your PG&E Job Owner will provide you with drawings that illustrate the trench route and specifications. Customers are responsible for trenching and permit costs.
- For more information about excavating a utility trench refer to the "Undergrounding Construction FAQs."
- Before you dig, call Underground Service Alert at 811, Monday through Friday from 6 a.m. to 7 p.m. except for holidays, or visit call811.
Contract execution and payment
Along with the project design, you will receive a contract, including an invoice for the project work to execute via DocuSign.
- Contracts must be executed within 90 days of receipt.
- Your contract, once executed, is valid for up to 12 months.
- Your design is valid for up to 18 months from issuance.
Construction scheduling
Work with your PG&E Job Owner to:
- Schedule any construction work to be completed by PG&E.
- Establish a new account if the location has not previously received gas service from PG&E.
Inspections and meter connection
Arrange for the appropriate local government agency to inspect the gas line. Once it has passed inspection, contact PG&E to schedule the meter connection.
Your home or business construction project may require temporary electric service to poles or posts for power. We can help provide power during building or renovation. PG&E can provide this service. Typically, your service can be connected within two weeks of receiving a completed application.
Submitting your application
- Apply for temporary electric service using Your Projects.
- Upload all required documents, including permits (if applicable) in the online application.
Application review
- Once you submit your application, a dedicated PG&E Job Owner is assigned to you. This person will become the point of contact for you or your contractor. PG&E recommends that you contact a contractor to help you plan your temporary service installation.
- A PG&E Job Owner will contact you within five business days. You or your contractor will be asked to supply details of the project. Details of the project include scope, timeline, blueprints, and the load requirements for appliances. You will need to provide details about any appliances or equipment you plan to install. Your PG&E Job Owner can answer additional questions. They can inform you of issues you may not have taken into consideration. Issues can be potential costs or technical Design Standards.
- If payment for an engineering advance is required, your PG&E Job Owner will notify you at this time.
- If necessary, a field meeting will be scheduled. PG&E uses the information you supply during a phone or on-site meeting to prepare a project design.
Note: You are required to provide all mandatory documents and materials. Deliver them to your PG&E Job Owner. Avoid application cancellation by submitting the documents within 35 calendar days. The document deadline date is no later than 35 days after you submit the application. Complete the application review process with your PG&E Job Owner. Complete it within 66 calendar days from application submission. The review deadline date is no later than 66 days after submission. This process complies with CPUC timeline regulations.
Contract execution and payment
- Once the costs have been determined, you will receive a contract, including an invoice for the project work to execute via DocuSign.
- Contracts must be executed within 90 days of receipt.
- Your contract, once executed, is valid for up to 12 months.
Installing temporary power
- Working with your contractor, install your temporary meter panel and pole, or post for your site in a location that is protected from hazards and vehicular traffic.
- Then contact your PG&E Job Owner to inspect your service installation. Inspect it prior to scheduling PG&E to energize your service.
- You or your contractor may need to refer to the Greenbook (PDF). The manual contains helpful information such as technical specifications and drawings. The following sections may be especially useful. Refer to them when preparing to install your temporary electric service:
- Temporary Overhead & Underground Electric Service: Details about the temporary service pole installation and grounding are in PG&E Design Standard 025055, "Requirements for Customer-Owned Poles."
Inspections and meter connection
Arrange for the appropriate local government agency to inspect the electric panel. Once it has passed inspection, contact PG&E to schedule the meter connection.
If your business construction project requires the installation of new electric service, PG&E can help. Get help to meet the technical requirements and coordinate your service installation. Depending on your city or county, you may have the option to choose your service. You may have the option to choose overhead service wires or underground service wires. Once you submit your application to PG&E, we will create a schedule to meet your service connection needs.
Selecting your rate
- All business customers are required to receive electric service on a general service rate. Customers can choose their rate based on monthly demand and usage patterns for gas or electric.
- Call if you are having trouble selecting the best rate for your business. Please contact the PG&E Business Customer Service Center at 1-800-468-4743.
Submitting your application
- Apply for new electric service using Your Projects.
- Upload all required documents, including permits (if applicable) in the online application.
Application review
- Once you submit your application, a dedicated PG&E Job Owner is assigned to you. This person will become the point of contact for you or your contractor. PG&E recommends that you contact a contractor to help you plan your new service installation.
- A PG&E Job Owner will contact you within five business days. You or your contractor will be asked to supply details of the project. Details of the project include scope, timeline, blueprints, and the load requirements for the electrical appliances. You will need to provide details about any or equipment you plan to install. Your PG&E Job Owner can answer additional questions. They can inform you of issues you may not have taken into consideration. Issues can be potential costs or technical Design Standards.
- If payment for an engineering advance is required, your PG&E Job Owner will notify you at this time.
- If necessary, a field meeting will be scheduled. PG&E uses the information you supply during a phone or on-site meeting to prepare a project design.
Note: You are required to provide all mandatory documents and materials. Deliver them to your PG&E Job Owner. Avoid application cancellation by submitting the documents within 35 calendar days. The document deadline date is no later than 35 days after you submit the application. Complete the application review process with your PG&E Job Owner. Complete it within 66 calendar days from application submission. The review deadline date is no later than 66 days after submission. This process complies with CPUC timeline regulations.
PG&E prepares project design
During the project design phase, we identify your costs and prepare construction drawings. We order critical materials with long lead times.
Additional references
You or your contractor may need to refer to the Greenbook (PDF). The following sections may be especially useful. Refer to them when preparing for your electric overhead service:
- Section 4: Overhead Electric Service
- Section 7: General Metering Information
Contract execution and payment
Along with the project design, you will receive a contract, including an invoice for the project work to execute via DocuSign.
- Contracts must be executed within 90 days of receipt.
- Your contract, once executed, is valid for up to 12 months.
- Your design is valid for up to 18 months from issuance.
Construction scheduling
Work with your PG&E Job Owner to:
- Schedule any construction work to be completed by PG&E.
- Establish a new account if the location has not previously received electric service from PG&E.
Inspections and meter connection
Arrange for the appropriate local government agency to inspect the electric panel. Once it has passed inspection, contact PG&E to schedule the meter connection.
If your business construction project requires the installation of new underground electric service, PG&E can help. Get help to meet the technical requirements and coordinate your service installation. Once you submit your application to PG&E, we will create a schedule to meet your service connection needs.
Selecting your rate
- All business customers are required to receive electric service at a general service rate. Customers can choose their rate based on monthly demand and usage patterns for gas or electric.
- Call if you are having trouble selecting the best rate for your business. Please contact the PG&E Business Customer Service Center at 1-800-468-4743.
Submitting your application
- Apply for new underground electric service using Your Projects.
- Upload all required documents, including permits (if applicable) in the online application.
Application review
- Once you submit your application, a dedicated PG&E Job Owner is assigned to you. This person will become the point of contact for you or your contractor. PG&E recommends that you contact a contractor to help you plan your new service installation.
- A PG&E Job Owner will contact you within five business days. You or your contractor will be asked to supply details of the project. Details of the project include scope, timeline, blueprints, and the load requirements for these appliances. You will need to provide details about any appliances or equipment you plan to install. Your PG&E Job Owner can answer additional questions. They can inform you of issues you may not have taken into consideration. Issues can be potential costs or technical Design Standards.
- If payment for an engineering advance is required, your PG&E Job Owner will notify you at this time.
- If necessary, a field meeting will be scheduled. PG&E uses the information you supply during a phone or on-site meeting to prepare a project design.
Note: You are required to provide all mandatory documents and materials. Deliver them to your PG&E Job Owner. Avoid application cancellation by submitting the documents within 35 calendar days. The document deadline date is no later than 35 days after you submit the application. Complete the application review process with your PG&E Job Owner. Complete it within 66 calendar days from application submission. The review deadline date is no later than 66 days after submission. This process complies with CPUC timeline regulations.
PG&E Prepares Project Design
During the project design phase, we identify your costs and prepare construction drawings. We order critical materials with long lead times.
Additional References
You or your contractor may need to refer to the Greenbook (PDF). The following sections may be especially useful. Refer to them when preparing for your electric underground service:
- Section 3: Underground Electric Service
- Section 7: General Metering Information
- Section 7: Electric Metering-Commercial and Industrial
- Electric Design Standard 063928, "Methods and Requirements for Installing Non-Residential Underground Services 0-600 V to Customer-Owned Facilities"
- Electric Design Standard 064309, "Box-Pad for Pad-Mounted Transformers"
Trenching
- Upgrading underground electrical lines may require the excavation of a trench. Your PG&E Job Owner will provide you with drawings that illustrate the trench route and specifications. Customers are responsible for trenching and permit costs.
- For more information about excavating a utility trench refer to the "Undergrounding Construction FAQs."
- Before you dig, call Underground Service Alert at 811, Monday through Friday from 6 a.m. to 7 p.m. except for holidays, or visit call811.
Contract execution and payment
Along with the project design, you will receive a contract, including an invoice for the project work to execute via DocuSign.
- Contracts must be executed within 90 days of receipt.
- Your contract, once executed, is valid for up to 12 months.
- Your design is valid for up to 18 months from issuance.
Construction scheduling
Work with your PG&E Job Owner to:
- Schedule any construction work to be completed by PG&E.
- Establish a new account if the location has not previously received electric service from PG&E.
Inspections and meter connection
Arrange for the appropriate local government agency to inspect the electric panel. Once it has passed inspection, contact PG&E to schedule the meter connection.
If you are making changes to your existing electric service at your business, PG&E can help. You may need help installing solar panels, adding new equipment, or upgrading your panel. Get help to meet the technical requirements and coordinate your service change. Once you submit your application to PG&E, we will create a schedule to meet your service connection needs.
Selecting your rate
- All business customers are required to receive electric service at a general service rate. Customers can choose their rate based on monthly demand and usage patterns for gas or electric.
- Call if you are having trouble selecting the best rate for your business. Please contact the PG&E Business Customer Service Center at 1-800-468-4743.
Submitting your application
- Apply for changes or upgrades to your existing electric service using Your Projects.
- Upload all required documents, including permits (if applicable) in the online application.
Application review
- Once you submit your application, a dedicated PG&E Job Owner is assigned to you. This person will become the point of contact for you or your contractor. PG&E recommends that you contact a contractor to help you plan your service change.
- A PG&E Job Owner will contact you within five business days. You or your contractor will be asked to supply details of the project. Details of the project include scope, timeline, blueprints, and the load requirements for appliances. You will need to provide details about any appliances or equipment you plan to install. Your PG&E Job Owner can answer additional questions. They can inform you of issues you may not have taken into consideration. Issues can be potential costs or technical Design Standards.
- If payment for an engineering advance is required, your PG&E Job Owner will notify you at this time.
- If necessary, a field meeting will be scheduled. PG&E uses the information you supply during a phone or on-site meeting to prepare a project design.
Note: You are required to provide all mandatory documents and materials. Deliver them to your PG&E Job Owner. Avoid application cancellation by submitting the documents within 35 calendar days. The document deadline date is no later than 35 days after you submit the application. Complete the application review process with your PG&E Job Owner. Complete it within 66 calendar days from application submission. The review deadline date is no later than 66 days after submission. This process complies with CPUC timeline regulations.
PG&E prepares project design
During the project design phase, we identify your costs and prepare construction drawings. We order critical materials with long lead times.
Additional references
You or your contractor may need to refer to the Greenbook (PDF). The following sections may be especially useful. Refer to them when preparing for your electric service:
- Section 4: Overhead Electric Service
- Section 3: Underground Electric Service
- Section 7: General Metering Information
- Electric Design Standard 063928, "Methods and Requirements for Installing Non-Residential Underground Services 0-600 V to Customer-Owned Facilities"
- Electric Design Standard 064309, "Box-Pad for Pad-Mounted Transformers"
Trenching
- Upgrading underground electrical lines may require the excavation of a trench. Your PG&E Job Owner will provide you with drawings that illustrate the trench route and specifications. Customers are responsible for trenching and permit costs.
- For more information about excavating a utility trench refer to the "Undergrounding Construction FAQs."
- Before you dig, call Underground Service Alert at 811, Monday through Friday from 6 a.m. to 7 p.m. except for holidays, or visit call811.
Contract execution and payment
- In certain situations, your PG&E Job Owner may find that there is no need to upgrade. Updates to your electric service or the utility facilities in your neighborhood are not necessary. You will be notified that there are no further steps to be taken.
- We may find that alterations need to be made to your overhead or underground electric service. Along with the project design, you will receive a contract including an invoice for the project work to execute via DocuSign.
- Contracts must be executed within 90 days of receipt.
- Your contract, once executed, is valid for up to 12 months.
- Your design is valid for up to 18 months from issuance.
Construction scheduling
Work with your PG&E Job Owner to schedule any construction work to be completed by PG&E.
Inspections and meter connection
Arrange for the appropriate local government agency to inspect the electric panel. Once it has passed inspection, contact PG&E to schedule the meter connection.
If you are beginning a construction project, it may be necessary to dig a trench. This allows for underground utility installations or upgrades. Gas and electric services are often installed in a joint trench. A trench may also contain other utility services like telephone and cable.
Examples of construction projects include:
- Building a home or adding rooms to your property or
- Installing appliances, air conditioners
- Installing electric vehicle charging station(s) or upgrading your meter panel
If the applicant chooses a trenching agent that is not PG&E, then PG&E requires applicants to use a licensed contractor as their trenching agent. If the trench fails to meet certain technical Design Standards, it will not pass PG&E's rigorous safety inspection. This may result in project delays and additional costs.
If you only need to stop service and remove the meter, call PG&E at 1-877-743-7782.
Submitting your application
- Request removals, upgrades or new gas service and underground electric services using Your Projects.
- Upload all required documents, including permits (if applicable) in the online application.
Application review
Once you submit your application, a dedicated PG&E Job Owner is assigned to you. This person will become the point of contact for you or your contractor.
- A PG&E Job Owner will contact you within five business days.
- If payment for an engineering advance is required, your PG&E Job Owner will notify you at this time.
- If necessary, a field meeting will be scheduled.
Note: You are required to provide all mandatory documents and materials. Deliver them to your PG&E Job Owner. Avoid application cancellation by submitting the documents within 35 calendar days. The document deadline date is no later than 35 days after you submit the application. Complete the application review process with your PG&E Job Owner. Complete it within 66 calendar days from application submission. The review deadline date is no later than 66 days after submission. This process complies with CPUC timeline regulations.
Before you begin trenching
- Your PG&E Job Owner will guide you through the project. They will provide a drawing that illustrates the trench route with specifications.
- Ahead of digging your trench, PG&E recommends that you schedule a pre-construction meeting., a meeting with the PG&E inspector and PG&E Job Owner. They will help you meet the technical Design Standards and pass the PG&E safety inspection.
- Notification: California law requires customers to notify utilities. Notification must be at least two working days before digging. Customers can notify all affected utility providers with a single call. The call is a free service offered by Underground Service Alert. Call 811, Monday through Friday from 6 a.m. to 7 p.m. except for holidays. For more details, visit Underground Service Alert (USA) or call811.
- References: You or your contractor may need to refer to the Greenbook (PDF). It is a reference manual containing helpful information. The Greenbook includes additional information, such as technical specifications and drawings. The following sections may be especially useful. Refer to them for a project that requires trenching:
- Section 3: Underground Electric Service
- Section 2: Gas Service
- PG&E Design Standard S5453, "Joint Trench," Joint Trench Configuration and Occupancy Guide
Contact your PG&E Job Owner immediately if you are unable to comply with the drawing. Or contact us if you are unable to comply with a written Design Standard. PG&E or your local government agency can provide the Design Standards.
General trenching requirements
- Safety: Make sure that trenches near pedestrian or vehicle traffic are barricaded to ensure safety. Call 811 before you dig to notify utilities to mark existing underground utility lines. This will help you avoid damaging the existing utility equipment underground when you dig.
- Separation: Provide at least three feet of horizontal separation from trenches. Trenches contain propane lines and sewer, water, or storm drainpipes. These are not permitted in a multiple utility trench.
- Trench Occupants: All equipment in a utility trench must be owned by an entity. That entity must be a member of the Underground Service Alert (USA). USA is a California organization that helps ensure public safety. They do so by coordinating location information about the buried utility lines. Private lines such as irrigation controllers and wires for outdoor lighting are not allowed in a joint trench.
- Excavation: Dig the trench according to the trench drawing and the Design Standards. The standards are found in Joint Trench Configuration and Occupancy Guide in PG&E Design Standard S5453. Access the "Joint Trench" section in the Electric and Gas Service Requirements in the Greenbook (PDF).
- Backfill: Backfill must provide a smooth bedding area for the utility lines. It must and must supply at least 12 inches of cover over the conduit or pipe. Make sure to use permitted material. Sand is recommended. Details on backfill can be found in the Joint Trench Configuration and Occupancy Guide in the Gas Design Standard S5453. Refer to Engineering Material Specification EMS-4123, "Backfill Sand."
- Conduit Installation: All conduit systems must pass PG&E's visual inspection. They must be tested for compliance. Test by inserting and pulling a flexible steel mandrel through the entire conduit system successfully. For details on mandrels refer to the Greenbook section titled Underground Electric Service.
Contract execution and payment
Along with the project design, you will receive a contract including an invoice for the project work to execute via DocuSign.
- Contracts must be executed within 90 days of receipt.
- Your contract, once executed, is valid for up to 12 months.
- Your design is valid for up to 18 months from issuance.
Construction scheduling
Work with your PG&E Job Owner to schedule any construction work to be completed by PG&E.
Overhead Construction
To determine if your pole is approved by PG&E, refer to:
- Table 1: "Approved Suppliers for Permanent Wood Poles," in PG&E Design Standard 025055, "Requirements for Customer-Owned Poles" for approved suppliers.
- Table 3: "Pole Setting Depths," shows the minimum and maximum depths to set poles by terrain and length of pole.
Generally, the following will determine the pole's approval status in the following table below:
Per PG&E Design Standard 025055, "Requirements for Customer-Owned Poles." Ground rods must be:
- At the base of the "customer-owned" pole and below the meter panel
- Installed no more than 12-inches from the pole
- Connected to the meter panel's ground terminations with a Grounding Electrode Conductor (ground wire)
To install a meter panel to a pole, see PG&E Design Standard 065374, "Overhead and Underground Panel Board Construction."
Installation
To setup the conduit mast per PG&E Design Standard 065374, "Overhead and Underground Panel Board Construction:"
- Use conduit PVC Schedule 40 (minimum)
- Securely fastened to the Heavy Duty 2-Hole Pipe Strap Every 36-inch
- Enter into the top of the meter panel or gutter (not the rear or side) of the meter panel
To set up the weatherhead:
- Be situated at the top of the conduit mast
- Provide a 36-inch curve, "drip loop," for service conductors
- Be installed at a height that meets clearance requirements
A "down guy bob" is a non-conductive equipment, also known as an insulator, used to segregate the tensioned wire to prevent electric current from running down the guy wire.
Installation:
According to PG&E Design Standard 022178, "Construction Requirements for Pole Line Guys," a down guy bob may be installed as per the following:
An anchor rod (also known as "guy anchor") is a device used to provide stability and support to a pole.
It is required to be installed when the following conditions are met per PG&E Design Standard 025055, "Requirements for Customer-Owned Poles:"
- Where conductors cross, a public or private paved street or road
- Non-paved (i.e., gravel, dirt) routes in agricultural areas
- Poles set in areas with soft soil
Underground Construction
- For backfilling material, competent native soil is preferred for bedding, shading, and backfilling throughout the trench. Native soil is preferred to help with corrosion, logistical, and affordability concerns. However, if the native material is deemed unsuitable, you must use PG&E-approved imported fine material. Or you can use sand that meets the requirements. The requirements are specified in Engineering Material Specification (EMS)-4123.
- The soil must be properly compacted according to specific requirements:
- For trenches across or along public roads, streets, or franchise areas: minimum 95% density compaction
- For trenches across private properties and all other areas: minimum 90% density compaction
- A Compaction Test Report may be required by PG&E. The report must include the testing company's name, address, and contact information.Special consideration should be given to trenches. Trenches that are on slopes or grades, where bags of concrete and red dye may be required. Concrete and red dye may be required on top of the conduit to prevent backfill movement.
- Then, place "warning tape" above the sand. See PG&E Design Standards 038193. See "Minimum Requirements for the Design and Installation of Electric Conduit, Insulated Cable, and Facilities."
- Finally, cover with native soil or additional imported sand until it meets the ground level.
Based on the type of trench (secondary/service/streetlight or primary), the minimum coverage will differ. See PG&E Design Standards 038193, "Minimum Requirements for the Design and Installation of Electric Conduit, Insulated Cable, and Facilities" for measurement details.
Refer to Table 3, "Minimum Separation and Clearance for Electrical Conduit by Facility Type" Then refer to PG&E Design Standard 038193. See "Minimum Requirements for the Design and Installation of Electric Conduit, Insulated Cable, and Facilities."
For PVC-to-PVC conduit connections, refer to Table 1, "Cement for Use with Plastic Conduits" in PG&E Design Standard 062288, "Underground Conduits."
There is a 315-degrees maximum bend allowed. This per PG&E Design Standard 038193, "Minimum Requirements for the Design and Installation of Electric Conduit, Insulated Cable, and Facilities." It is allowed for service conduit up to 200 feet.
For service conduits longer than 200 feet, the maximum bend is 300-degrees.
For example, to compute the degree of conduit bend for services conduits longer than 200 feet:
- Sum all angles of the bends in the conduit run ("box-to-panel")
- 90-degree refers to Design Standard elbow
- 45-degree refers to half elbow
- 30-degree
- 22.5-degree
- or 11.25-degree refers to smooth sweeps
- Ensure that the total degree is less than or equal to 300-degrees
Conduit end bell is a fitting that is installed at the end of the conduit. It prevents cable damage when cable is pulled through the conduit and while in service.
See additional details in PG&E Design Standard 062288, "Underground Conduits."
"Working Space" refers to the clear and level area in front of, around, and above underground electrical equipment. For example, transformers, switchgear, and enclosures. Working space allows safe access for operation, inspection, and maintenance.
See working space requirements in PG&E Design Standard 051122, "Clearances and Location Requirements for Enclosures, Pads, and Underground Equipment," and 2026 Greenbook, Table 7-4, "Metering Working Space Dimensional Requirements."
Follow the checklist outlined in PG&E Design Standard 063927, "Methods and Requirements for Installing Residential Underground Electric Services 0-600 V to Customer-Owned Facilities:"
- Confirm the meter panel is properly rated for your building (i.e., 120/240 volts, 120/208 volts, etc.).
- Verify you have an approved meter panel by checking the label. Ensure it states the panel has been certified as "Underwrites Laboratories-Listed (UL)." Or that the meter panel is tested by a National Recognized Testing Laboratory. This ensures the meter panel meets the Occupational Safety and Health Administration (OSHA). Check that the meter panel has met PG&E Greenbook requirements.
- Ensure the panel location is:
- On an exterior wall, readily accessible
- Not behind fences, inside garages, or obstructed by other objects
- 36-inches of clear working space in front of the meter and 78-inches above the ground
- Mounted with the meter's center 48-inches to 75-inches above finished grade
- Not within 36" of a home window
- Ensure ground rods, clamps, wires, and bonding wires are installed properly. Refer to California Electrical Code (CEC). Also refer to and PG&E Design Standard 013109, "Corrosion Resistant Ground Rods and Ground Rod Clamps" for more information.
- Ensure the neutral and ground are bonded together only in the main breaker (main switch) section of the main panel.
- Ensure the panel is sealed from water intrusion. Do so by by sealing conduits at both ends and using an approved method per PG&E Design Standard 062288, "Underground Conduits."
- Properly labeling the panel in accordance with Greenbook Section 7.7.1., "Properly Identifying and Marking Meters." The panel must have a permanent, weather-resistant address label. The labels must be clearly visible from the street or access point.
- Pass local City/County inspections.
Per Section 7.9, "Grounding," of the Greenbook, customers ground their meter panel by:
- Not using PG&E's gas equipment to ground the electric equipment
- Locating the disconnection point, also known as "terminations" (e.g., ground terminal) for their Grounding Electrode Conductors (GECs). They are outside any section that PG&E seals.
- Grounding wire comes out of where the circuit breaker wires. These are the wires that lead into the home's outlets (also known as the "load side of the breaker")
- Not locating Grounding Electrodes, Grounding Electrode Conductors, or Grounding Ring Conductors inside or near any PG&E electrical equipment, enclosures, or vaults.
- Ensuring a grounded neutral connection exists in the PG&E-sealed meter section. Ensure it is terminated in the same enclosure as the Grounding Electrode Conductor.
The responsibilities for an inspection of a ground meter panel:
A "drain box" is also referenced as a "splice box/enclosure or #2 box/enclosure" which measures 17" x 30" and 26" deep. The purpose of this box is to allow any water that may enter the conduit system to drain out of the box which prevents the water from running into the meter panel and building.
Installation
- Install drain box next to the meter panel or within 6-feet of the meter panel along the service run. This standard is per PG&E Design Standard 063927, "Methods and Requirements for Installing Residential Underground Electric Services 0-600 V to Customer-Owned Facilities,"
- Place the box on 12-inch base of 1-inch rock. This facilitates water drainage. Then organize the conduits in a horizontal layout.
Maintain a minimum depth from finished grade to top of the conduit:- 18-inches for existing installations
- 24-inches for new installations
- See PG&E Design Standard 063927, Figure 1, "Methods and Requirements for Installing Residential Underground Electric Services 0-600 V to Customer-Owned Facilities," for additional details.
- Per PG&E Design Standard 025055, "Requirements for Customer-Owned Poles," conduit couplers or joints need to be 6-inches below and need to be swept up 90-degrees against the pole.
- The conduit must be either rigid galvanized steel if "floating" (not attached to pole or structure) or 2-inch minimum diameter Schedule 40 PVC if attached to the pole or structure.
- The conduit must be strapped to the pole. This is for earthquake safety.
More building and renovation resources
The application and new service project process
Understand the PG&E building and renovation process step by step.
Applicant Installer Pre-qualification requirements
Get information about the applicant installer prequalification requirements.
Applicant Designer Program
More information on applicant design and installer qualifications.
This website and the messages contained in its webpages are funded by customers unless otherwise noted.
©2026 Pacific Gas and Electric Company
©2026 Pacific Gas and Electric Company