IMPORTANT

Moraga-Oakland X 115 kV Rebuild Project

Improving safety and reliability for customers in Orinda, Oakland and Piedmont

In November 2024, PG&E submitted the project application and Proponent’s Environmental Assessment (PEA) to the California Public Utilities Commission (CPUC) Energy Division. View PG&E’s Application (A.24-11-005) and PEA here.

Project status

PG&E is committed to providing safe and reliable energy to our customers. As part of that commitment, we are planning to rebuild electrical equipment between the Moraga Substation in Orinda and Oakland X Substation in Oakland.


If approved, this project will rebuild approximately five miles of aging electrical equipment. These upgrades will help PG&E maintain a safer and more reliable system. 

 

Map of the Moraga Oakland Project

Our work with the community

In spring of 2024, PG&E hosted a series of open houses for customers interested in learning more about the project. Through these open houses, PG&E was able to listen and collect thoughtful feedback about the proposed project as well as answer questions from the community.

Frequently asked questions

We are replacing decades-old electrical equipment with new structures that are stronger. In some locations, the structures will have greater ground-to-conductor clearances. These taller structures will help meet increased requirements that improve safety and reduce wildfire risk. This project is a key component of PG&E’s efforts to upgrade its infrastructure and meet the needs of the region’s energy demands.

The proposed project covers approximately five miles from the Moraga Substation in Orinda, through a portion of unincorporated Contra Costa County and Oakland’s Shepherd Canyon neighborhood, a small section of Piedmont and ends at the Oakland X Substation on Park Boulevard in Oakland.

PG&E’s project team submitted a permit application to the CPUC for approval in November 2024. The CPUC will conduct its own review of the application and prepare a draft environmental document. The CPUC’s process is expected to take 24-36 months with opportunities for public input, including commenting on the draft environmental document, before the final permit is issued. If approved, project construction could begin in 2027. Construction will be a phased approach and will begin and end in different areas. It is expected to be completed in 2029.

A chart outlining steps for the project

Project benefits

  • Replacing aging infrastructure with new, stronger equipment will create a safer system for PG&E customers.
  • Modernizing transmission lines will ensure PG&E exceeds the highest industry standards for reliability.
  • New transmission lines are expected to accommodate the region’s future energy demands. 

Additional resources

Before you dig, know what’s below

Call Underground Service Alert (USA) at 811 at least two working days before you dig.