©2026 Pacific Gas and Electric Company
Error: Field cannot be left blank.
Error: Invalid entry. Do not use equal signs [=] or colons [:].
This summary is not available. For more details, open this PDF.
- Still need assistance? Try the Help Center.
- Link accounts. Learn how to link your accounts or access more accounts.
- CARE. Find out if you qualify for a discount.
- Medical Baseline. Learn how to apply.
- Rebates. Explore PG&E rebates for your home.
- Outages. Report and view electric outages.
- Jobs/Careers. Find out about jobs at PG&E.
Error: Field cannot be left blank.
Error: Invalid entry. Do not use equal signs [=] or colons [:].
This summary is not available. For more details, open this PDF.
- Still need assistance? Try the Help Center.
- Link accounts. Learn how to link your accounts or access more accounts.
- CARE. Find out if you qualify for a discount.
- Medical Baseline. Learn how to apply.
- Rebates. Explore PG&E rebates for your home.
- Outages. Report and view electric outages.
- Jobs/Careers. Find out about jobs at PG&E.
The U.S. is in the middle of the biggest wave of electricity demand growth in decades. Much of that growth is being driven by the digital infrastructure behind cloud computing, artificial intelligence and advanced technologies. For California, that creates both a challenge and an opportunity: how to power the next generation of innovation in a way that is fast, reliable, affordable and consistent with the state’s clean energy goals.
For data center developers, speed to power has become one of the defining constraints. Cost still matters, but it is no longer the only deciding factor. The best sites also need available capacity, a clear path to interconnection, proximity to customers and talent, operational flexibility and access to clean energy at scale.
California's story is more competitive than many people think.
The common assumption is that building in California will be harder, slower and more expensive. The reality is more nuanced. Northern California already has the customers, talent, fiber networks, clean energy foundation and innovation ecosystem that many data center operators need. PG&E's job is to make sure the grid is ready for that demand—and that we connect it in a way that works for existing customers, too.
That means identifying where capacity is available today, streamlining how new load connects, investing where growth is real and building flexibility into how projects come online. Just as important, it has to work for the customers and communities already here.
The goal is not simply to serve more load. It is to serve new demand in a way that improves grid utilization, supports affordability, strengthens reliability and helps California remain a place where the world's most important technologies are built.
Those priorities—speed, certainty, clean energy and long-term partnership—are also where PG&E has the most to offer, starting with something many developers do not expect: room on the grid that already exists.
Our grid has room—and that's good news for customers
One of California's biggest advantages is one many people do not expect: PG&E's grid has available capacity today. That is intentional because the grid was designed and built to serve peak demand, but until recently, we haven't had the mechanisms to flex that peak at scale. On average, the grid operates at about 40–45% of capacity, which means in several parts of our service territory we can connect 50–100 megawatts of new demand using infrastructure that is already in place.
That does not mean every project can connect immediately or everywhere. But it does mean some projects can move faster than developers may expect in California, especially when they are sited in areas where capacity already exists.
The real challenge is not whether power exists on the system. It is making sure the right infrastructure is available in the right place at the right time. That is why PG&E is working with developers early to identify locations with available capacity today while continuing to invest in the transmission and substation upgrades needed to support future growth.
Speed and certainty matter as much as cost
Across the country, data center development is increasingly constrained by how quickly power can be delivered. PG&E is focused on reducing that uncertainty by identifying near-term capacity, streamlining studies and aligning infrastructure planning earlier, so developers can move from proposal to operation with greater confidence.
Using the existing grid well is also what turns new demand into a benefit for the customers already on the system. When large, steady users such asdata centers connect to a grid with available capacity, they can help spread the fixed costs of operating and maintaining that grid across more customers. Under the right conditions, PG&E estimates each 1 GW of new demand can reduce bills by about 1%, which is why we describe this as rate-reducing load growth.
Outside research reinforces the importance of getting this growth right. A roundtable led by Stanford University's Bits & Watts Initiative on rising AI-related electricity demand found that affordability and customer value must remain a top priority. Participants emphasized the importance of using existing grid capacity where possible and planning infrastructure investments carefully. The report also stressed that growth works best when customers can see clear benefits from it. The takeaway is that growth is most sustainable when it creates value for new customers, as well as the communities and customers already connected to the grid.
The benefits are not automatic. They depend on available infrastructure and thoughtful planning. But they reinforce the core point: when new, consistent demand is added to a system with available capacity, it can help put downward pressure on rates.
The way large new customers connect is also designed to protect customers already on the system:
- In our service area, many data center projects are 100 MW or smaller, which means they can plug into infrastructure we already have.
- Under the interim Rule 30, PG&E's interim framework for connecting large new loads, transmission-level customers fund the interconnection infrastructure their projects require upfront, while final refund and cost-allocation details remain under regulatory review.
- Refunds are tied to projects actually coming online and generating revenue, helping reduce the risk that existing customers pay for projects that do not materialize.
There are also checks and balances built into the process. PG&E does not unilaterally decide how much demand is forecast or which transmission projects get built. Those decisions are subject to independent planning and regulatory review, and projects can be modified as demand projections change. The goal is to invest where growth is real while protecting customers from paying for infrastructure that is not needed.
The bottom line: customers can benefit from this growth when new load is connected in the right places, under the right structure and with planning that keeps pace with actual demand.
That is why the next question is not simply how much demand is coming, but how PG&E plans for it responsibly, building where growth is real, avoiding unnecessary investment and keeping flexibility at the center of the strategy.
Real benefits for real communities
Data centers are not just large electricity users. When planned well and connected responsibly, they can bring tangible benefits to the communities where they operate, including jobs, local tax revenue, infrastructure investment and long-term economic activity that supports public services and local businesses.
A typical 40 MW facility can:
- Create nearly 700 construction jobs, including opportunities for skilled trades and local contractors.
- Support 135 permanent positions tied to ongoing operations, maintenance and facility support.
- Generate $5–$7 million in annual property tax revenue that can help fund local priorities such as schools, public safety, roads, parks and other community services.
- Add $10–$20 million in sales tax revenue, supporting city and county budgets and the services residents rely on.
If communities are going to host new infrastructure, they should see real benefits from it. PG&E's role is to help make sure new data center demand is connected in ways that protect existing customers, support reliability, attract related investment in local infrastructure and create broader value for the places we serve.
Planning ahead for real demand
The level of interest is real. In 2026, PG&E's data center pipeline grew from about 5.1 GW at the end of March to roughly 12.7 GW as of June 30, a sharp increase that reflects how quickly the market is moving and how seriously companies are looking at Northern and Central California.
But a pipeline is not the same as committed load. About 8.2 GW of the 12.7 GW is still early, sitting in application or preliminary engineering. About 3.9 GW is in final engineering, the last step before construction starts where developers have made a more meaningful commitment through work performance agreements. Roughly 490 MW has reached interconnection construction agreements, and about 140 MW is under active construction.
That is why PG&E does not treat every application as a project that will ultimately be built. A large pipeline is a strong indication of demand, but not every application becomes an energized facility. Responsible planning means moving quickly where projects are ready while avoiding the two risks that hurt customers most: overbuilding for projects that never materialize or under-planning in places where demand is already taking shape.
PG&E expects to serve approximately 1.8 GW of new data center load by 2030. The opportunity is real. The key is matching investment to the projects, places and timelines most likely to move forward.
That is why planning ahead does not just mean planning for the biggest possible number. It means using better information, clearer customer commitments and more flexible tools to decide where to move now, where to prepare next and where to wait for stronger signals:
- Advanced load forecasting to understand how electrification, AI, data centers and advanced manufacturing could affect the grid over time.
- Stage-gated project review to separate early interest from projects with stronger commercial and engineering commitments.
- Cluster studies that group nearby projects together, so we can plan around real geographic demand instead of studying each request in isolation.
- Optimizing what we have before building something new, which helps unlock more value from existing infrastructure and reduces the risk of unnecessary investment.
Turning flexibility into an advantage
Flexibility is one way PG&E can move faster without getting ahead of actual demand. We have been investing in flexible interconnection for years, from Flex Connect at the distribution level to T-Flex at the transmission level. The goal is simple: make better use of the grid we already have, connect ready projects sooner and align infrastructure investment with actual demand.
In practice, flexibility can mean coming online in stages. Some customers may eventually need significant amounts of power, but only a portion of that load when operations begin. By working with customers on phased ramp-ups and flexible operating approaches, PG&E can often support earlier energization while larger infrastructure upgrades move forward.
It also means treating flexible load management as part of the business model. Customers that can shift, manage or reduce load during peak periods may be able to access options that support reliability, lower costs over time and create a faster path to power.
The benefit is practical: flexibility gives developers more ways to scale, gives PG&E better tools to manage demand and helps customers benefit from growth without forcing every project into the same all-or-nothing timeline.
Building smart, not just building more
Over the next five years, PG&E is planning to invest more than $20 billion to keep up with growing electricity demand from data centers, electric vehicles, building electrification and other sources, while continuing to improve service for existing customers. But building smart also means recognizing that not every solution requires a new line, substation or large construction project.
PG&E is investing where the grid needs to grow and using technology and planning tools to get more out of the system we already have.
That matters in places like San José, where electricity demand is expected to nearly triple over the next decade. PG&E is preparing to invest $2.4 billion in transmission and distribution upgrades across the South Bay, but the strategy is not simply to build more. It is to build in the right places, at the right time, and in ways that support growth without creating unnecessary costs for customers.
Technology can help accelerate that work. At the Los Esteros substation, SmartValve® power flow controllers are being installed to enable more than 100 MW of additional capacity by redirecting power to underused lines with no major new construction required. It is a practical example of the larger approach: unlock capacity where we can, build where we must and keep projects moving while longer-term infrastructure catches up.
There is still major work ahead, especially in high-demand areas like Silicon Valley and the South Bay. The approach is straightforward: combine targeted investment, grid-enhancing technology and flexible ways to connect customers so California can support growth faster and more responsibly. And as more large customers come online, that same focus has to carry through to the most important measure of all: reliability.
Prioritizing reliability
Growth only works if the grid remains dependable for the customers and communities already here. That is why reliability is central to PG&E's data center strategy and why investment in the existing system continues alongside new load. In San José, PG&E's 2025 reliability upgrades reduced outage durations by 20%, showing how targeted work on the existing system can improve service today while preparing for future demand.
That work includes practical upgrades across the system:
- New and upgraded transformers, substation equipment and other grid assets that strengthen local capacity.
- Automated switching technology, including FLISR, that can isolate faults quickly so fewer customers are affected.
- Targeted inspections, maintenance and grid hardening to reduce the risk of outages before they happen.
- Direct coordination with large-load customers on flexible load management and on-site backup resources that support reliability during peak conditions.
Moving forward together and meeting the moment
More electricity demand does not have to conflict with California's climate goals. Done right, it can help accelerate the clean energy transition by funding grid upgrades, renewable energy and flexible technologies. And if these data centers are not built on California's cleaner grid, they will be built elsewhere with much higher emissions.
That matters for data center operators, many of which have committed to 24/7 carbon-free energy. California's cleaner grid and PG&E's growing portfolio of renewable and zero-carbon resources make that goal more achievable here than in many other regions.
That is why PG&E is working with customers and local partners on solutions that support both growth and decarbonization, including:
- District energy systems that can make large campuses more efficient.
- Microgrids and on-site resources that can support reliability and resilience.
- Flexible connection options that help customers come online in stages.
- Load management tools that can reduce peak demand and lower emissions over time.
PG&E is on track for a net-zero energy system by 2040. The point is not that demand growth is simple. It is that growth, decarbonization and affordability must be planned together.
That is how California can support the next generation of digital infrastructure while continuing to move toward a cleaner grid.
California now must answer a practical question: how do we power the next wave of digital infrastructure while making the grid stronger and more affordable for everyone who depends on it?
PG&E's approach is to use available capacity where it exists, invest where the grid needs to grow, build flexibility into how projects come online and plan carefully to avoid unnecessary costs.
Developers may come for different reasons, including speed to power, proximity to customers, access to talent or a cleaner grid, but increasingly it is the combination of those factors that makes California competitive. PG&E's role is to make sure that strength translates into real projects, real customer benefits and real community value.
For developers, the most useful next step is an early conversation. The sooner PG&E understands a project's location, size and ramp-up timeline, the sooner we can pinpoint where capacity already exists, where flexible interconnection can accelerate energization and where infrastructure work needs to begin.
That is how California can turn demand growth into an opportunity: by building a grid that is more resilient, more affordable, cleaner and ready for what comes next.