Operating Data | Pipeline Maintenance

Pipeline Maintenance News

As of Thursday, March 23, 2023

Redwood Path Maintenance
Dates
Capacity
(MMcf/d)
Maintenance Notes
March 22 - 27
1570
Delevan Station Maintenance
March 28
1970
Delevan Station Maintenance
April 04 - 07
2200
Bethany Station Maintenance
April 12 - 13
2060
Tionesta Station Maintenance
April 14
2150
Tionesta Station Maintenance
April 16
2210
Delevan Station Maintenance
April 17
2090
Delevan Station Maintenance
April 18
2120
Delevan Station Maintenance
Gerber Station Maintenance
April 19
2070
Gerber Station Maintenance
April 20
2160
Gerber Station Maintenance
April 24
2190
Burney Station Maintenance
April 25 - 27
2020
Burney Station Maintenance
March Max Capacity: 2260
April Max Capacity: 2250
View Max Capacities for All Months
Baja Path Maintenance
Dates
Capacity(MMcf/d)
Maintenance Notes
Kettleman Hinkley Topock
March 22 - 28
788
788
975
L-300A Pipeline Maintenance
L-300B Pipeline Maintenance
March 29
788
600
975
L-300A Pipeline Maintenance
L-300B Pipeline Maintenance
Hinkley Station Maintenance
March 30
450
400
975
L-300A Pipeline Maintenance
L-300B Pipeline Maintenance
Hinkley Station Maintenance
March 31
788
788
975
L-300A Pipeline Maintenance
L-300B Pipeline Maintenance
April 01 - 30
380
788
975
L-300A Pipeline Maintenance
L-300B Pipeline Maintenance
Kettleman Station Maintenance
March Max Capacity: 975
April Max Capacity: 975
View Max Capacities for All Months

Limitations at Specific Interconnect Points:

Redwood Path
Dates Capacity
(MMcf/d)
Maintenance Notes
March 22 - 270Net withdrawal Wild Goose storage facility
March 28554Net withdrawal Wild Goose storage facility
March 22 - 270Net withdrawal from Central Valley storage facility
March 28175Net withdrawal from Central Valley storage facility
Baja Path
Dates Capacity
(MMcf/d)
Maintenance Notes

Physical Pipeline Capacity shows daily physical capacity at the various interconnections to CGT. Pipeline Maintenance News details maintenance events on CGT's backbone transmission pipelines and the corresponding forecast capacity reductions on the Redwood and Baja paths.

Storage Maintenance:

Injection
Dates Available Injection
(MMcf/d)
Maintenance Notes
Withdrawal
Dates Available Withdrawal
(MMcf/d)
Maintenance Notes

Download Pipeline Maintenance History

and preceding Days In Excel

Maintenance will not appear in the archive until after it's been removed from the Operating Data | Pipeline Maintenance page above. You can download Redwood and Baja pipeline maintenance information as far back as November 1, 2016. You can download Limitations at Specific Interconnect Point information as far back as March 21, 2018. You can download Storage Maintenance information as far back as December 11, 2020.

Prospective Maintenance Document

Last revised: March 16, 2023

Download our Prospective Maintenance document for a 6-12 month outlook of proposed maintenance on the CGT pipeline system. Note that this document is revised monthly and is offered in addition to our existing month-out Pipeline Maintenance information listed above.