Operating Data | Pipeline Maintenance

Pipeline Maintenance News

As of Thursday, July 19, 2018

(Any day not shown is at 100% capacity)


Redwood Path Maintenance
Dates Capacity
(MMcf/d)
% of MaxMaintenance Notes
July 19197994 % L-400/401 Maintenance
Gerber Station Maintenance
Tionesta Station Maintenance
July 20205098 % L-400/401 Maintenance
Gerber Station Maintenance
July 21 - 31206799 % Gerber Station Maintenance
August 01 - 13206998 % Gerber Station Maintenance
August 14199395 % Tionesta Station Maintenance
Gerber Station Maintenance
August 15 - 16206998 % Gerber Station Maintenance
August 20209099 % L-400 Pipeline Maintenance
August 21208999 % L-400 Pipeline Maintenance
Delevan Station Maintenance
August 22195393 % L-400 Pipeline Maintenance
Delevan Station Maintenance
Burney Station Maintenance
August 23202397 % L-400 Pipeline Maintenance
Burney Station Maintenance
August 24 - 31209099 % L-400 Pipeline Maintenance

Redwood Maximum Pipeline Capacities
January2232May2147September2119
February2222June2121October2157
March2205July2097November2199
April2181August2095December2230

Baja Path Maintenance
Dates Capacity
(MMcf/d)
% of MaxMaintenance Notes
July 19 - 3147041 % Unplanned L-300B Pipeline Repair
L-300A Pipeline Maintenance
August 01 - 0747041 % Unplanned L-300B Pipeline Repair
L-300A Pipeline Maintenance
L-300A/B Station Maintenance
August 08 - 3154047 % Unplanned L-300B Pipeline Repair
L-300A Pipeline Maintenance
L-300A/B Station Maintenance

Baja Maximum Pipeline Capacities
January1107May1153September1145
February1105June1145October1146
March1097July1134November1089
April1146August1139December1107


Limitations at Specific Interconnect Points:

Redwood Path
Dates Capacity
(MMcf/d)
Maintenance Notes
Baja Path
Dates Capacity
(MMcf/d)
Maintenance Notes
July 12 - 310Kramer Junction On-System Only
July 12 - 31676El Paso & Transwestern Interconnect at Topock Station limited
August 01 - 31676El Paso & Transwestern Interconnect at Topock Station limited
August 210KRGT - Daggett Interconnect limited

Physical Pipeline Capacity shows daily physical capacity at the various interconnections to CGT. Pipeline Maintenance News details maintenance events on CGT's backbone transmission pipelines and the corresponding forecast capacity reductions on the Redwood and Baja paths.

Download Pipeline Maintenance History

and preceding Days In Excel

Maintenance will not appear in the archive until after it's been removed from the Operating Data | Pipeline Maintenance page above. You can download Redwood and Baja pipeline maintenance information as far back as November 1, 2016. You can download Limitations at Specific Interconnect Point information as far back as March 21, 2018.

Prospective Maintenance Document

Last revised: July 18, 2018

Download our Prospective Maintenance document for a 6-12 month outlook of proposed maintenance on the CGT pipeline system. Note that this document is revised monthly and is offered in addition to our existing month-out Pipeline Maintenance information listed above.