Operating Data | Pipeline Maintenance

Pipeline Maintenance News

As of Friday, June 26, 2020

(Any day not shown is at 100% capacity)


Redwood Path Maintenance
Dates
Capacity
(MMcf/d)
Maintenance Notes
June 26
2060
Delevan Station Maintenance
July 08 - 17
1580
L401 In-Line Inspection Upgrade
July 27
2150
Gerber Station Maintenance
July 28 - 30
2070
Gerber Station Maintenance
July 31
2120
Gerber Station Maintenance
June Max Capacity: 2190
July Max Capacity: 2170
View Max Capacities for All Months
Baja Path Maintenance
Dates
Capacity(MMcf/d)
Maintenance Notes
Kettleman Hinkley Topock
June 26 - 30
650
480
600
L300A Pressure Reduction
L300B Pressure Reduction
Topock Station Maintenance
July 01 - 20
650
480
600
L300A Pressure Reduction
Topock Station Maintenance
July 21 - 22
650
480
600
L300A Pressure Reduction
Topock Station Maintenance
Hinkley Station Maintenance
July 23 - 24
500
350
600
L300A Pressure Reduction
Topock Station Maintenance
Hinkley Station Maintenance
July 25 - 31
650
480
600
L300A Pressure Reduction
Topock Station Maintenance
June Max Capacity: 1005
July Max Capacity: 1005
View Max Capacities for All Months

Limitations at Specific Interconnect Points:

Redwood Path
Dates Capacity
(MMcf/d)
Maintenance Notes
July 08 - 170Wild Goose & Central Valley Storage Withdrawal
Baja Path
Dates Capacity
(MMcf/d)
Maintenance Notes

Physical Pipeline Capacity shows daily physical capacity at the various interconnections to CGT. Pipeline Maintenance News details maintenance events on CGT's backbone transmission pipelines and the corresponding forecast capacity reductions on the Redwood and Baja paths.

Download Pipeline Maintenance History

and preceding Days In Excel

Maintenance will not appear in the archive until after it's been removed from the Operating Data | Pipeline Maintenance page above. You can download Redwood and Baja pipeline maintenance information as far back as November 1, 2016. You can download Limitations at Specific Interconnect Point information as far back as March 21, 2018.

Prospective Maintenance Document

Last revised: June 18, 2020

Download our Prospective Maintenance document for a 6-12 month outlook of proposed maintenance on the CGT pipeline system. Note that this document is revised monthly and is offered in addition to our existing month-out Pipeline Maintenance information listed above.