Operating Data | Pipeline Maintenance

Pipeline Maintenance News

As of Thursday, June 20, 2019

(Any day not shown is at 100% capacity)


Redwood Path Maintenance
Dates
Capacity
(MMcf/d)
Maintenance Notes
July 02
2010
Tionesta Station Maintenance
July 03
2100
Tionesta Station Maintenance
July 08 - 14
1950
L-401 Pipeline Maintenance
July 16 - 23
1770
L-400 Pipeline Maintenance
July Max Capacity: 2170
View Max Capacities for All Months
Baja Path Maintenance
Dates
Capacity(MMcf/d)
Maintenance Notes
Kettleman Hinkley Topock
June 20
600
745
1005
Kettleman Station Maintenance
Unplanned Hinkley Station Maintenance
L-300B Pipeline Maintenance
June 21
700
745
1005
Kettleman Station Maintenance
Unplanned Hinkley Station Maintenance
L-300B Pipeline Maintenance
June 22 - 30
830
830
1005
Kettleman Station Maintenance
Unplanned Hinkley Station Maintenance
July 01 - 11
830
830
1005
Kettleman Station Maintenance
Hinkley Station Maintenance
July 12 - 15
810
530
1005
Kettleman Station Maintenance
Hinkley Station Maintenance
L-300B Pipeline Maintenance
July 16 - 17
455
530
1005
Kettleman Station Maintenance
Hinkley Station Maintenance
L-300B Pipeline Maintenance
July 18
690
530
1005
Kettleman Station Maintenance
Hinkley Station Maintenance
L-300B Pipeline Maintenance
July 19 - 24
770
770
1005
Kettleman Station Maintenance
Hinkley Station Maintenance
L-300B Pipeline Maintenance
July 25 - 28
830
830
1005
Kettleman Station Maintenance
Hinkley Station Maintenance
July 29 - 31
730
730
1005
Kettleman Station Maintenance
Hinkley Station Maintenance
L-300B Pipeline Maintenance
June Max Capacity: 1005
July Max Capacity: 1005
View Max Capacities for All Months

Limitations at Specific Interconnect Points:

Redwood Path
Dates Capacity
(MMcf/d)
Maintenance Notes
Baja Path
Dates Capacity
(MMcf/d)
Maintenance Notes
July 29 - 310Daggett Interconnect reduced to ZERO.

Physical Pipeline Capacity shows daily physical capacity at the various interconnections to CGT. Pipeline Maintenance News details maintenance events on CGT's backbone transmission pipelines and the corresponding forecast capacity reductions on the Redwood and Baja paths.

Download Pipeline Maintenance History

and preceding Days In Excel

Maintenance will not appear in the archive until after it's been removed from the Operating Data | Pipeline Maintenance page above. You can download Redwood and Baja pipeline maintenance information as far back as November 1, 2016. You can download Limitations at Specific Interconnect Point information as far back as March 21, 2018.

Prospective Maintenance Document

Last revised: June 17, 2019

Download our Prospective Maintenance document for a 6-12 month outlook of proposed maintenance on the CGT pipeline system. Note that this document is revised monthly and is offered in addition to our existing month-out Pipeline Maintenance information listed above.