Wednesday, December 24, 2014
On December 23, 2014, PG&E submitted Advice Letter 3547-G to the California Public Utilities Commission, which includes the backbone transportation and storage rates that will be effective on January 1, 2015.
Although PG&E's California Gas Transmission will be updating the Pipe Ranger Rates pages next week, we wanted to make the 2015 rates information available to you as soon as possible. As you may recall from our Rate Case Update article in July, these rates are interim rates, effective until we get the final resolution of the 2015 Gas Transmission and Storage Rate Case.
For your reference, below is a table of the Firm Backbone (G-AFT, MFV rate design) rates.
2014 Rates | Rates Effective January 1, 2015 | |
Redwood to On-System - Core | ||
Reservation Charge ($/Dth/Mo) | $4.5126 | $4.9663 |
Usage Charge ($/Dth) | $0.0705 | $0.0749 |
Total ($/Dth @ Full Contract) | $0.2188 | $0.2382 |
Redwood to On-System - Noncore | ||
Reservation Charge ($/Dth/Mo) | $5.2050 | $5.7105 |
Usage Charge ($/Dth) | $0.0952 | $0.1018 |
Total ($/Dth @ Full Contract) | $0.2663 | $0.2896 |
Baja to On-System - Core | ||
Reservation Charge ($/Dth/Mo) | $5.3466 | $5.8170 |
Usage Charge ($/Dth) | $0.0831 | $0.0878 |
Total ($/Dth @ Full Contract) | $0.2588 | $0.2790 |
Baja to On-System - Noncore | ||
Reservation Charge ($/Dth/Mo) | $5.9939 | $6.5151 |
Usage Charge ($/Dth) | $0.1093 | $0.1162 |
Total ($/Dth @ Full Contract) | $0.3063 | $0.3304 |
Silverado and Mission to On-System | ||
Reservation Charge ($/Dth/Mo) | $3.1566 | $3.4544 |
Usage Charge ($/Dth) | $0.0500 | $0.0522 |
Total ($/Dth @ Full Contract) | $0.1538 | $0.1657 |
Please contact your CGT Sales Representative with any questions.