South County Power Connect will serve our 43,000 electric customers in Morgan Hill, Gilroy and southern Santa Clara County. This map provides an overview of the project components and project study area, including the eight potential substation sites and refined transmission line corridors identified by the project team.


Project breakdown


  • Construct a new substation
  • Connect Morgan Hill-Llagas 115 kV line into the new substation
  • Connect one of the Metcalf-Moss Landing 230 kV lines into the new substation
  • Reconductor the 115 kV line from the new substation to the existing Morgan Hill Substation

July 2016 – Substation Site Options and Refined Transmission Line Corridors


In July 2016, we presented a project map with eight substation site options and refined transmission line corridors. Please click below to view the map shared at the July 2016 public open houses.


South County Substation Site Options and Refined Transmission Line Corridors in July 2016


February 2016 – Substation Study Area and Potential Transmission Line Corridors


In February 2016, we presented a project map with a substation study area and potential transmission line corridors. Please click below to view the substation study area and potential corridor map shared at the February 2016 public open houses.


South County Substation Study Area and Potential Transmission Line Corridors in February 2016


September 2015 – Project Study Area


In September 2015, we hosted our first round of public open houses. At the open houses, the project team presented the project study area map, which identified the large section of land in which the project could reasonably be located. Please click below to view the original project study area map.


South County Project study area in September 2015