Event | Date/Time |
---|---|
RFO Issuance | December 1, 2014 |
Deadline to register for Participants' Conference | December 16, 2014 |
Participants' Conference | December 18, 2014 |
Notice of Intent (NOI) Submittal Deadline | January 5, 2015 |
Offer Form Webinar | January 15, 2015 |
Offer Submittal Deadline via Power Advocate | February 17, 2015, 1 PM PPT |
Participants Notified of Eligibility for Shortlisted Offer Negotiations | April 24, 2015 |
Target Deadline to Execute Agreements | October 1, 2015 |
File Application with the CPUC | December 1, 2015 |
On December 18, 2014, PG&E held a Participants' Conference on the 2014 Energy Storage RFO in PG&E's auditorium.
All Participants interested in submitting an offer package will need to pre-register with Power Advocate before submitting an Offer into the RFO. To register at Power Advocate, click on the following link:
Power Advocate Link (Event 46155: 2014 Energy Storage RFO)
Participants must successfully register with Power Advocate to submit an offer into the Energy Storage RFO. We strongly encourage you to register now.
For information or questions on the Energy Storage RFO, email EnergyStorage@pge.com and the Independent Evaluator, at waynejoliver@aol.com.
To receive notices about this RFO, return to PG&E's main RFO website and click the Request to be added to PG&E's RFO Distribution List Form link.
PG&E encourages potential Participants to enter the applicable electric interconnection process (transmission or distribution) as soon as practicable.
For questions related to electric interconnection, email wholesalegen@pge.com.
The Generator Interconnection Procedure pursuant to the WDT and CAISO Tariff consists of three application processes: (1) The “Fast Track Procedure for generators 5 MW (2 MW on 12kV, 3MW on 21kV, and 5MW on higher voltages) in size that pass the “Fast Track Screens," (2) the Independent Study Process for all generators that are electrically independent from another generator or cluster of generators, and (3) the Cluster Study Process for interconnection requests that do not qualify for the Fast Track Process or the Independent Study Process.
Under the CAISO Tariff and PG&E WDT Generator Interconnection Procedures, all interconnection requests under the Independent Study Process or Cluster Process may request interconnection as a “full capacity” resource. Please refer to PG&E’s or CAISO’s website for more details.
Any application for interconnection to PG&E can be submitted through an online form available at PG&E's Customer Connections Online page. Visit Customer Connections Online.