The CSI program has a 2-step and 3-step application process depending on the customer segment and system size.

2-Step Application Process

For (1) all retrofit, residential projects, regardless of system size and (2) for retrofit or new construction, non-residential projects (commercial, industrial, agricultural, government, non-profit and public entities) with a system size of < 10 kW.

Step 1: Submit the Reservation Request Form (RRF) and all required documents.

This step is to reserve funding for the project. An approval notification will be sent within 30 days.*

Step 2: Once installation is complete and the system is interconnected, submit the Incentive Claim Form (ICF) and all required documents.

This step is to request payment of your incentive. ICF must be submitted within 1 year (residential) or 18 months (non-residential) of reservation. An approval notification will be sent within 30 days.*

3-Step Application Process

For all retrofit or new construction, non-residential projects (commercial, industrial, agricultural, government, non-profit and public entities) with a system size of > 10 kW.

Step 1: Same as 2-Step Application Process, however application fee will be required.

Step 2: Submit the Proof of Project Milestone and all required documents.

This step is to show progress of the project and allow ample time to secure a purchase/installation contract.

Step 3: Same as 2-Step Application Process.


*Missing or incorrect information/documents may cause delays.

Note: All projects may be subject to a field verification inspection. This must be completed before the incentive payment is made.

Application Forms

Links to all the documents and forms you’ll need including the CSI applications and supporting documentation.