Generator Interconnection Request

Welcome to the Rule 21 Export Online Application Web Portal for electric generators. This option to submit your application electronically is an intermediate solution as PG&E's Electric Generation Interconnection (EGI) Department works to transition to a 100% web-based application.

On the next page you will find the Rule 21 Export Application (Form 79-1145) for generation that will sell under a PURPA Power Purchase Agreement.

Submitting your Application through the online form requires you do so in one session.

There are three steps to completing the online form. An application checklist is available for guidance.

The first step of the Interconnection Request entails entering information into a web-based form. This part of the application takes approximately 15 minutes.

The second step of the Interconnection Request entails uploading documents needed to complete your application: the project details in Attachnment A; a Single Line Diagram; Site Drawing; Site Exclusivity; AC/DC Schematics; and a Description of Operations.

The final step certifies that the application was prepared by the individual completing the online form, and that all of the content entered is true and correct.

PG&E strongly recommends preparing all information and materials before starting the online application. If the Interconnection Request is missing information or documents required to begin the generator interconnection process, PG&E will accept the application, but will deem it incomplete. PG&E will provide a written list of deficiencies to the designated representative provided in your request. Failure to submit subsequent information pursuant to Rule 21 will result in the withdrawal of the Interconnection Request.

Questions concerning PG&E's Online Application process can be directed to the Electric Generation Interconnection Department at rule21gen@pge.com.

The following information will be submitted via an online application process at PG&E's website

Note: Due to the nature of the online submission, certain information on the online application form may be required.

Step 1: Application Type & Contact Step 2: Generating Facility Info Step 3: Attachments & Submit

Application Type

* indicates required field

The undersigned Applicant submits this request to interconnect its Generating Facility with the Pacific Gas and Electric Company (PG&E or Distribution Provider) Distribution System pursuant to Rule 21 for:*

Detailed Study Process
Fast Track Process

This Interconnection Request is for*

Contact Information

* indicates required field

Primary Customer Contact (person who will be contacted):

Representative Facility Contact (i.e. General Contractor):

Same as Primary Customer Contact?:*

Site address of existing or proposed generating facility project:

PV/RAM Map
PV/RAM Map

Maximum net megawatt (MW) electrical output:

(MW)
(MW)

Project type and equipment configuration in net megawatts:

(MW)
(MW)
(MW)
(MW)
(MW)
(MW)
(MW)
(MW)
(MW)

Proposed operation dates (must be sequential):

Approximate location of the proposed Point of Interconnection:

PV/RAM Map

AC Disconnect Switch. List the AC disconnect switch that will be used at this Generating Facility
(enter "N/A" if not applicable):

Please attach the following documents to this application.

Preparer

Enter legal name and title of the submitter of this request.

Agreement