2004 Long Term RFO - Facility Ownership
Most recent update to Announcements: 4/25/05
Most recent update to Q&A: 4/22/05
Pacific Gas and Electric Company ("PG&E") is considering purchase of newly built dispatchable generation facilities with commercial availability beginning in 2008, 2009, or 2010. In this 2004 Long Term Request for Offers - Facility Ownership (the "RFO"), PG&E is seeking Offers from Participants pursuant to which PG&E would enter into agreements to purchase such facilities. Parties interested in submitting Offers in response to this RFO are referred to PG&E's RFO and related data and information described below.
2004 Long Term RFO - Facility Ownership Schedule
Updated 3/18/05
| Event | Date |
|---|---|
| Re-Publication of Final RFO | March 18, 2005 |
| Deadline to Initiate Interconnection Studies | March 28, 2005 |
| Participants Asked to Submit Notice of Intent to Offer | April 8, 2005 |
| Deadline for Respondents to Submit Initial Offers | April 27, 2005 |
2004 Long Term RFO - Facility Ownership and Appendices (All Updated 3-18-05)
- Request for Offers (RFO) (PDF, 105 KB)
- Composite of All Appendices to RFO (3/21: change to Appendix B, Appendices F2 and F3 resequenced) (PDF, 564 KB)
- Appendices to RFO
- Appendix A, Long Term Facility Ownership Request for Offers Agreement and Confidentiality Agreement (revised 4/22/05) (PDF, 41 KB)
- Appendix B, Form of Letter of Credit (revised 4/25/05)
- Appendix C, Notice of Intent to Offer Form
- Appendix D1, Purchase and Sale Agreement Term Sheet
- Appendix D2, HBPP Purchase and Sale Agreement Term Sheet
- Appendix E, Offer Data Form
- Appendix F1, Project Data Sheets
- Appendix F2, Project Description
- Appendix F3, Pro Forma
- Appendix G, Credit and Finance Information Form
- Appendix H, Electric Transmission Information Form and Web Links
- Appendix I, Gas Interconnection Information Forms
- Appendix J, Functional Specifications
- Appendix J, Exhibit J1, Functional Specifications - HBPP
- Appendix K, Offer Cover Sheet
Transmission Related Information and References
- Generation Interconnection Information and References
- Electric Transmission Proxy Costs and Reports and Q&A (updated 6/14/05)
Pre-Bid Conference - October 15
- Participants Conference Presentation – October 15, 2004 (PDF, 81 KB) Please review Q&A below in conjunction with the conference presentation. The Conference Presentation is superceded in its entirety by the RFO.
Announcements and Updates
- 2004 Long Term RFO: Announcements and Updates (updated 4/25/05)
Questions and Answers
- 2004 Long Term RFO: Questions and Answers (updated 4/22/05)
Contact Us
For information or questions about this PG&E 2004 Long Term RFO:
E-Mail to: ownershiprfo@pge.com